November 2, 2018

PLEASE NOTE:  The following schedule is weather and production dependent.

UPDATE:  The South Street project is moving along.  The curbs have been poured and asphalt has begun to be laid.  Paving should be completed next week.

 

There are no residences or structures within the area that will be closed.  Access to parcels south of South Street will be available via Keslinger Road and Thryselius.  The property developer will provide proper notifications, signage and barricades during this time frame.  Parkside, Saratoga, and Cambridge will remain open during the two week construction period.