7/16/2021 – Cambridge Update – all work is weather dependent
• Paving was cancelled on Thursday (July 15) due to rain.
• Concrete contractor is in the process of cleaning up and stripping forms.
• No parking signs have been removed from streets where paving is complete.
• Weather permitting, Builders Paving will finish paving remaining streets on Friday (July 16).

 

Village of Elburn 2021 Streets Program

The 2021 Village of Elburn Streets Program is about to kick off. The attached color-coded map ( 2021 Streets Program Location Map ) shows streets that will receive crack sealing or be resurfaced.

Work will begin in the Cambridge Subdivision (near Lions Park) and the tentative start date is June 21, 2021. All work is weather dependent.

Updates regarding the work and schedule will be posted on the Village website ( https://www.elburn.il.us/ ) as they become available.

Questions may be directed to the Village of Elburn Public Works Department at 630-365-5064.

2021 Streets Program Location Map